Construction and Infrastructure Disputes in China

Construction and infrastructure disputes in China turn on contract validity, final accounts, delay and the contractor's priority right over the project. A new Supreme People's Court interpretation in force since 30 June 2026 changes several rules on tendering, price adjustment and audit-based payment, so contracts and claims strategies deserve a fresh look.

10 min read Updated
EN中文

Key takeaways

  • The Civil Code's chapter on construction contracts and two SPC interpretations form the core legal framework.
  • The SPC's Interpretation (II) took effect on 30 June 2026 and applies to newly accepted first-instance cases.
  • Fixed-price contracts generally do not adjust for labour or material rises unless expressly agreed.
  • The contractor's priority right must be exercised within 18 months of the date payment fell due.
  • Court-appointed cost appraisal frequently decides valuation disputes, so the project record is critical.
  • Purely domestic contracts usually cannot be arbitrated outside the mainland.

How construction and infrastructure disputes in China are decided

Construction and infrastructure disputes in China are usually about money, time and quality: unpaid progress payments and final accounts, delay and acceleration, variations, defects, and the allocation of risk when prices or ground conditions change. They are decided by the people's courts or, where the contract contains a valid arbitration clause, by a Chinese or international arbitral tribunal. In either forum the starting point is the Civil Code, which since 1 January 2021 has contained a dedicated chapter on construction project contracts, supplemented by detailed judicial interpretations from the Supreme People's Court (SPC).

Three features make the Chinese environment distinctive for foreign contractors, employers, investors and lenders. First, the validity of the contract itself is often in play, because rules on mandatory tendering, contractor qualifications and subcontracting are strictly enforced and a breach can render the contract void. Second, valuation disputes are frequently resolved through court-appointed cost appraisal rather than party expert evidence alone. Third, contractors enjoy a statutory priority right over the proceeds of the project they built, which interacts with mortgages held by banks and the rights of home buyers.

Engineers reviewing site records for construction and infrastructure disputes on a Shenzhen project
Payment, delay and defects claims dominate construction and infrastructure disputes on Chinese projects.

For a foreign party, the practical question is rarely which rule applies in the abstract. It is whether the contract, the project records and the dispute clause will hold up when a claim is made, and whether security can be obtained early enough to make an eventual award or judgment worth having. The sections below set out the legal framework as at November 2026, the main recurring issues, the forums available, and the steps that tend to decide outcomes. Specific PRC law questions should always be confirmed with a licensed PRC law firm.

The core rules sit in the Civil Code, Book III, Chapter 18 on construction project contracts. These provisions cover contract formation, the prohibition on unlawful transfer and subcontracting, completion acceptance, payment, and the contractor's priority right over the project. Where a construction contract is void but the works pass acceptance, the Civil Code allows the contractor to be compensated by reference to the agreed price, so invalidity does not necessarily wipe out the commercial bargain. General contract rules, including change of circumstances and penalty adjustment, also apply.

The Tendering and Bidding Law determines which projects must be procured through public tender, which commonly includes infrastructure, public utilities and projects funded by state capital above specified values. Construction law and regulations govern contractor qualification grades and site safety, and the Regulations on Ensuring Payment of Wages to Migrant Workers, in force since 1 May 2020, impose dedicated wage accounts and joint responsibilities on general contractors.

The SPC's Interpretation (I) on construction contract disputes, effective 1 January 2021, remains the backbone of judicial practice. It deals with matters such as the effect of unlawful tenders, the date of completion, how to value works when a contract is void, and the time limit for exercising the contractor's priority right, which may not exceed 18 months from the date on which the employer should have paid. In 2026 the SPC added a second interpretation, discussed below, which changes several practical rules for new cases.

A further instrument matters for payment claims. The revised Regulations on Ensuring Payment to Small and Medium-sized Enterprises, issued by the State Council and in force since 1 June 2025, set a 60-day payment deadline in the situations they cover, restrict the use of commercial bills to delay payment, and prohibit making payment to a small or medium-sized supplier conditional on receiving payment from a third party. Back-to-back and pay-when-paid clauses in subcontracts with such suppliers therefore need careful review.

What the SPC's 2026 interpretation changes

On 29 June 2026 the SPC issued its Interpretation (II) on the application of law in the trial of construction contract disputes, which took effect on 30 June 2026. It applies to first-instance cases accepted after that date, and where it differs from earlier interpretations it prevails. For anyone currently negotiating, administering or preparing claims under Chinese construction contracts, it is the most important development since the Civil Code.

IssueDirection of the 2026 interpretationPractical effect
Projects that required tender but were not tenderedA contract should not be held void solely for lack of tender if, when the claim is brought, the project no longer falls within the mandatory tender scopeFewer opportunistic invalidity arguments based on outdated tender thresholds
Substantive negotiation before awardNegotiating key terms before the award, or signing first and tendering afterwards, can make the winning bid contract voidPre-award side agreements remain high risk
Borrowed qualificationsContracts using another contractor's qualification are void; the lender cannot recover a fee; compensation for the actual builder depends on quality and the employer's knowledgeEmployers should verify who is really performing the work
Fixed-price contractsLabour and material price movements are generally not adjusted unless the contract provides for it or change of circumstances appliesPrice adjustment clauses must be drafted expressly
Termination of lump-sum contractsCompleted work may be valued as a proportion of the fixed total price, derived from the pricing standardClearer valuation on termination
Payment tied to government auditIf an audit result is delayed for reasons not attributable to the contractor or plainly departs from the contract, the contractor may apply for judicial cost appraisal; the reasonable period is capped at one year from submission of completion settlement documentsIndefinite audit delays are less effective as a defence
Retention moneyThe return period runs from the contractor's exit from site, or from termination if laterClearer start date for retention claims
Priority rightThe amount claimed must be specified; standby and idle-time losses caused by the employer are not covered; insurance proceeds and compensation can be subject to the rightPriority claims need careful quantification

The interpretation also addresses unlawful transfers and subcontracts, generally steering compensation claims by the party that took such work towards the contractor that let it rather than an employer with which it has no contract, and it confirms routes for migrant workers to recover unpaid wages from the developer, general contractor or subcontractor. Because the rules apply by reference to the date a case is accepted, the timing of filing can matter where a dispute straddles 30 June 2026.

Common issues in construction and infrastructure disputes

Most construction and infrastructure disputes in China turn on a handful of recurring questions. Recognising them early helps parties preserve the right evidence and avoid arguments that will not succeed.

  • Final account and valuation. Disagreement over the settlement price is the single most common claim. Where the parties cannot agree and the contract does not resolve the method, courts and tribunals frequently appoint a cost appraisal institution, whose report then carries considerable weight.
  • Validity of the contract. Unlawful tendering, borrowed qualifications, unlawful subcontracting and so-called "yin-yang" contracts (a filed contract and a private side contract on different terms) can each lead to invalidity and a different basis of valuation.
  • Delay and time extensions. Claims depend heavily on contemporaneous notices, site visas (signed instructions or confirmations) and meeting minutes. Formal time-bar clauses are generally enforced where clearly agreed, subject to arguments about waiver and conduct.
  • Variations and site visas. Unsigned instructions are a recurring weakness for contractors; unsigned approvals are a recurring weakness for employers that later deny them.
  • Quality and defects. Liability can survive completion acceptance; defects liability periods and retention arrangements are frequently disputed.
  • Price fluctuation. Under the 2026 interpretation, labour and material price rises in fixed-price contracts are generally for the contractor's account unless the contract says otherwise or the change of circumstances doctrine applies.
  • Bonds and guarantees. Calls on performance bonds and advance payment guarantees, and applications to restrain them, are often the first flashpoint.
Practical point

Many construction claims in China are won or lost on the quality of the project file rather than on legal argument. Before a dispute crystallises, collect the signed contract and any filed version, all site visas and variation orders, payment certificates, meeting minutes, correspondence with the supervising engineer, completion acceptance records and audit submissions. Translate key documents early, because a court-appointed cost appraiser will work from the Chinese record.

Forums: courts, arbitration and dispute boards

A domestic construction contract between two Chinese entities, including foreign-invested enterprises, will usually be resolved in mainland China, either before the people's court where the project is located or before a Chinese arbitral institution. Disputes over construction project contracts are commonly allocated to the court where the project sits, so a contractor on a project in an inland province may face local litigation if there is no arbitration clause. The revised Arbitration Law, effective 1 March 2026, introduces the concept of the seat, recognises online proceedings and shortens the period to apply to set aside an award to three months.

Foreign-related contracts, such as an international EPC contract between a Chinese contractor and an overseas employer, can choose arbitration abroad or in the mainland. Institutions such as CIETAC and the Shenzhen Court of International Arbitration (SCIA) handle a large volume of construction cases, as do the HKIAC and SIAC for regional projects. Our pages on domestic arbitration in China and international arbitration explain how to choose between them.

Dispute boards, common under FIDIC forms, are increasingly used on internationally financed projects. Their decisions are usually binding unless and until revised by arbitration, and a failure to refer a dispute to the board, or to give a notice of dissatisfaction in time, can bar a later claim. Chinese contractors working abroad on FIDIC-based contracts should treat the dispute board timetable as strictly as any limitation period.

ForumTypical useKey strengthsKey cautions
People's court where the project is locatedDomestic contracts without an arbitration clause; priority right claimsPreservation and enforcement power; two-tier reviewLocal influence concerns; cost appraisal drives the outcome
CIETAC, SCIA or local commissionDomestic and foreign-related contracts with a mainland clauseSpecialist arbitrators; confidentiality; final awardInterim measures still ordered by courts
HKIAC, SIAC or ICCForeign-related EPC and infrastructure contractsNeutral seat; enforcement under the New York ConventionGenerally unavailable for purely domestic disputes
Dispute boardFIDIC-based and multilateral-bank funded projectsReal-time decisions during the worksStrict referral and notice deadlines

Infrastructure, PPP and cross-border projects

Large infrastructure disputes add further layers. Government-and-social-capital cooperation (PPP) projects and concession-style arrangements raise questions about whether a dispute is contractual and arbitrable, or administrative and therefore subject to administrative litigation. Claims arising from a government counterparty's unilateral changes, early termination or failure to pay availability fees may need to be analysed through both lenses. Our pages on PPP projects and administrative litigation and reconsideration discuss these boundaries.

For Chinese contractors abroad, the issues reverse. Projects under the Belt and Road framework are often built under FIDIC-style contracts governed by a host-state law or English law, financed by Chinese policy banks or export credit agencies, and subject to multilateral development bank procurement and integrity rules. Construction and infrastructure disputes on these projects can involve parallel claims against the employer, the host state under an investment treaty, and insurers, as well as the risk of debarment. See our pages on international projects and overseas EPC and Belt and Road.

The SPC has also built specialist capacity. The China International Commercial Court, with benches in Shenzhen and Xi'an, was established in 2018 to hear major international commercial cases and works with selected arbitral and mediation institutions as a "one-stop" platform. Since 1 January 2024, amendments to the Civil Procedure Law have expanded the jurisdiction of Chinese courts over foreign-related cases and clarified service and evidence-gathering abroad, which matters when a foreign employer or parent guarantor must be brought into proceedings.

Managing a construction claim step by step

Whether the client is an employer, contractor, lender or investor, the sequence below reflects how construction and infrastructure disputes tend to unfold in practice and where decisions have the greatest effect.

  1. Diagnose the contract. Confirm which documents form the contract, whether a filed version differs from the signed one, whether tender rules applied, and whether any party lacked the right qualification. Validity determines the valuation basis.
  2. Check the dispute clause and pre-conditions. Identify negotiation periods, engineer or dispute board steps, and notice requirements. Under the revised Arbitration Law the clause should still name an institution and, ideally, a seat.
  3. Secure the position. Consider property preservation against bank accounts or receivables, and evaluate the priority right within its 18-month window. Preservation is ordered by courts and usually requires security.
  4. Quantify early. Prepare a reasoned final account and claims for delay, variations and disruption. Anticipate the cost appraisal process and the questions an appraiser will ask.
  5. Explore settlement. Mediation, including court-annexed and institutional mediation, resolves a large share of construction cases; see our page on mediation.
  6. Plan enforcement. Map the counterparty's assets, any guarantees, and whether enforcement will be needed in Hong Kong or abroad.

Common mistakes include relying on unsigned site instructions, missing contractual notice deadlines, accepting a final audit without reserving rights, overlooking the 18-month priority window, and assuming that a foreign seat is available for a dispute between two Chinese subsidiaries. Each of these is avoidable with early attention.

How TRW & Co helps with construction and infrastructure disputes

TRW & Co's Shenzhen representative office helps foreign employers, contractors, investors and lenders, and Chinese contractors working abroad, to manage construction and infrastructure disputes from the first signs of trouble. We review contracts and project records against international practice, build claims strategy and quantum narratives, advise on English law, Hong Kong law and other non-PRC laws governing EPC, FIDIC and financing documents, and prepare for international arbitration and dispute board procedures. Where PRC legal advice, court filings, preservation applications or representation before mainland courts or tribunals are required, we coordinate closely with licensed PRC law firms and keep the whole team aligned on strategy and budget. To discuss a project, please contact us.

Frequently asked questions

Can a foreign-invested contractor in China choose Hong Kong arbitration for a dispute with a Chinese developer?

Usually not, if both parties are Chinese legal persons and the project is in the mainland, because the dispute is then treated as domestic. Foreign-invested enterprises are Chinese legal persons. Limited exceptions exist, for example for some enterprises registered in pilot free trade zones. Where a foreign parent, foreign lender or overseas element is genuinely involved, a foreign seat may be available, but the position should be checked with PRC counsel before the contract is signed.

What is the contractor's priority right and how does it rank?

The Civil Code gives a contractor a priority right to be paid the price of the works from the proceeds of auction or discounted sale of the project it built. It generally ranks ahead of mortgages over the project, but the SPC has confirmed that home buyers who have paid in full for homes they intend to live in rank ahead of both. The right must be exercised within a limited period, capped at 18 months from when payment was due.

Does a government audit clause stop a contractor from claiming payment?

Not indefinitely. Clauses tying final payment to a government audit are common on publicly funded projects. Under the SPC's 2026 interpretation, if the audit result is delayed for reasons not attributable to the contractor, or is plainly inconsistent with the contract, the contractor may ask the court for a judicial cost appraisal. The reasonable waiting period is capped at one year from submission of the completion settlement documents.

Are pay-when-paid clauses enforceable in China?

It depends on the parties. The revised Regulations on Ensuring Payment to Small and Medium-sized Enterprises, in force since 1 June 2025, prohibit making payment to a small or medium-sized supplier conditional on payment by a third party. Between larger enterprises such clauses are assessed under general contract law. Main contractors should review their subcontract templates, because a clause that is unenforceable against a smaller subcontractor offers no protection.

How long does a construction case usually take?

Simple payment claims can conclude within months, especially through mediation. Larger disputes involving cost appraisal, counterclaims for defects and multiple parties often take one to two years at first instance or in arbitration, and appeals or set-aside applications add further time. Early preservation and a well-organised project record are the most effective ways to shorten the process.

Sources

  1. Supreme People's Court: Interpretation (II) on construction project contract disputes (2026)
  2. National Database of Laws and Regulations: Civil Code of the PRC
  3. Xinhua: revised Regulations on Ensuring Payment to SMEs
  4. China International Commercial Court
  5. CIETAC

General information only, not legal advice. TRW & Co’s Shenzhen representative office does not provide PRC legal services; where a PRC legal opinion is required we work with licensed PRC law firms.

Email the China deskinfo@trw.co WhatsAppMessage our team