Regulated Access to Infrastructure in China

Access to infrastructure in China is governed by two overlapping regimes: sector rules that require pipelines, grids and networks to open to third parties, and the Anti-Monopoly Law, which treats an unjustified refusal to share an essential facility as abuse of dominance. Users and operators need to understand both, because the remedies and regulators differ.

9 min read Updated
EN中文

Key takeaways

  • The Anti-Monopoly Law treats refusing reasonable access to an essential facility as a possible abuse of dominance.
  • SAMR's 2023 abuse of dominance provisions list the factors used to identify an essential facility.
  • The Energy Law, in force since 1 January 2025, underpins fair-access duties for energy networks.
  • NDRC Order No. 33 on oil and gas pipeline access took effect on 1 November 2025, with written reasons for refusals.
  • New NEA pipeline disclosure and reporting measures are due to apply from 1 January 2027.

How access to infrastructure in China is regulated

Access to infrastructure in China means the right of a third party, such as a gas trader, an independent power producer, a telecoms reseller or a logistics operator, to use a network or facility owned by someone else on reasonable terms. Two bodies of rules apply. The first is sector regulation: laws and departmental rules that oblige operators of pipelines, grids, terminals and similar assets to open capacity to qualified users without discrimination, under the supervision of a sector regulator such as the National Energy Administration (NEA) or the Ministry of Industry and Information Technology.

The second is competition law. Under the Anti-Monopoly Law, as amended with effect from 1 August 2022, a dominant undertaking that refuses to deal without a legitimate reason may be committing an abuse, and the State Administration for Market Regulation (SAMR) and its provincial bureaux can investigate.

LNG terminal and pipeline network illustrating third-party access to infrastructure in China
Pipelines, terminals and grids are the classic bottlenecks; digital gateways now raise the same questions.

The two regimes are complementary rather than alternative. A sector rule may set tariffs, capacity procedures and disclosure duties in detail, while competition law polices conduct that falls outside or between those rules, such as tying, discriminatory terms or refusing access to a facility that no sector rule yet covers. For users, the practical question is which route offers the fastest and most credible remedy; for owners and investors, it is how to run an asset so that neither route is triggered.

Essential facilities under the Anti-Monopoly Law

SAMR's Provisions on the Prohibition of Abuse of Dominant Market Positions (SAMR Order No. 66, effective 15 April 2023) expressly list, among forms of refusal to deal, refusing to allow a counterparty to use an essential facility on reasonable terms. When deciding whether a facility is essential, the authority considers, in summary:

  • whether it is feasible to build or develop a comparable facility with reasonable investment;
  • how far the counterparty depends on the facility to carry on its business effectively;
  • whether the dominant undertaking is able to provide access; and
  • the effect that providing access would have on the undertaking's own operations.

The same provisions confirm that dominant undertakings may not use data, algorithms, technology or platform rules to carry out the listed abuses, which brings digital gateways within the same logic as physical networks. The Anti-Monopoly Law also contains a specific provision for industries controlled by the state-owned economy that bear on the national economy or national security: the state protects lawful operations in those sectors but also supervises their conduct and pricing, and operators may not use their control or exclusive position to harm consumers.

The essential facilities analysis only starts once dominance is established, so a complainant must first define the relevant market and show the operator's position in it. For a single pipeline or terminal serving a region, that is often straightforward; for logistics hubs, data centres or platforms, market definition is usually the main battleground. Under the amended law, abuse of dominance can lead to an order to stop, confiscation of illegal gains and a fine of between 1% and 10% of the previous year's sales. For a fuller treatment of dominance cases see our page on abuse of dominance.

Sector rules on access to infrastructure in China

The Measures for the Supervision of Fair and Open Access to Oil and Gas Pipeline Network Facilities (NDRC Order No. 33), issued under the Energy Law and effective 1 November 2025, are now the most detailed access code. Operators must serve qualified users fairly and may not refuse service where they have spare capacity; transmission, storage and regasification must be separated financially from sales; capacity allocation rules must be published; and contracts may not contain unfair terms. Unused contracted capacity is treated as released, and users that hoard capacity or provide false information also face penalties. Urban gas distribution networks are outside the scope of these measures.

Key mechanics of the pipeline measures

TopicRule under NDRC Order No. 33
Registration and applicationsOperators set and publish user registration conditions, application procedures and capacity allocation rules, and are encouraged to accept applications online
Response timeFor distributed or temporary capacity requests, a reply within five working days of receiving the application
RefusalsA rejected application, or termination of an accepted one, must be explained in writing with reasons
Over-subscriptionAllocation by clear rules, which may take account of application order, service period and heating season; results reported to the energy authority
InformationAccess rules, registration conditions and prices published; remaining capacity and operating data available to users on request; quarterly reporting of access status
DisputesCoordination by a provincial-level or higher energy authority, or proceedings in court
PenaltiesOperators that fail to correct breaches face fines of up to twice the affected party's loss, and RMB 100,000 to 200,000 for disclosure and reporting failures; users face fines of up to RMB 100,000

Similar principles apply elsewhere, although the level of detail varies:

SectorMain access instrumentsLead regulatorTypical issues
Oil and gas pipelines, LNG terminals, storageEnergy Law; NDRC Order No. 33 (from 1 November 2025); NEA disclosure and reporting measures (from 1 January 2027)NDRC, NEA and its regional offices, provincial energy authoritiesCapacity allocation, separation from trading, tariff application, information on spare capacity
Power gridsEnergy Law, Electricity Law and grid connection rulesNEA, NDRC (pricing)Connection of renewables and storage, dispatch, transmission and distribution tariffs
Telecoms networksTelecommunications Regulations and interconnection rulesMIITInterconnection, wholesale access for resellers, licensing of value-added services
Urban gas, water and heatingLocal franchise and utility rules; Anti-Monopoly LawLocal authorities; SAMR and provincial bureauxTying of installation services, connection charges, designated contractors
Ports, rail and digital platformsSector rules; Anti-Monopoly Law and SAMR provisions on data and platform rulesMinistry of Transport, SAMRDiscriminatory terms, self-preferencing, refusal of interoperability

In September 2026 the NEA published separate measures on information disclosure and reporting for pipeline fair access, applying from 1 January 2027, which divide information into categories published to the public, released to registered users and reported to the regulator. Users should expect more granular capacity data from 2027, and operators should be building the systems to produce it now.

Power, telecoms and digital gateways

Outside oil and gas, access to infrastructure in China is governed by less detailed rules. In power, grid companies must connect qualifying generators, including renewables and storage, under connection standards and approved transmission and distribution tariffs, with the NEA and its regional offices supervising fair dispatch and access. Disputes typically concern connection timing, the cost of grid reinforcement and curtailment. Developers should treat grid connection as a critical path item in project documents and financing, not a formality.

In telecoms, the basic carriers own the core networks and interconnection is regulated by MIIT. Foreign participation in value-added telecoms services is shaped by licensing and the foreign investment negative list, so access questions are often bound up with whether the business can be licensed at all. For digital gateways such as app stores, payment systems and large platforms, SAMR's provisions on data, algorithms and platform rules mean that refusing interoperability or applying discriminatory terms can be examined in the same way as a physical bottleneck. This makes access to infrastructure in China a live issue for technology businesses as well as energy companies.

Common access disputes and enforcement

Access problems tend to fall into recurring patterns: an operator claims there is no capacity; it offers access only with conditions such as buying its own gas, equipment or installation services; it charges different users different rates for equivalent service; or it delays signing contracts until the user's commercial window has passed. Local utility tying, where a gas or water supplier requires customers to use designated contractors for connection works, has been a frequent subject of provincial market regulation enforcement.

Remedies differ by route. A complaint to the sector regulator may lead to an order to provide service and administrative penalties under the access rules. A complaint to SAMR may lead to an Anti-Monopoly Law investigation, commitments or fines. A civil claim before a PRC court is also possible under the Anti-Monopoly Law, and under the pipeline measures parties may ask a provincial-level energy authority to mediate or go to court. Which route works best depends on evidence, timing and the commercial relationship. Our page on private antitrust litigation explains the court route.

Choosing a route

RouteBest suited toMain limitations
Sector regulator complaintClear breach of a published access code, such as no written reasons or ignored deadlinesLimited to the sector rules; penalties focus on correction rather than compensation
SAMR or provincial bureau complaintWider competition concerns, tying, discrimination, facilities outside any access codeAuthority decides whether and when to act; dominance must be shown
Civil claim in courtRecovering losses and obtaining binding ordersBurden of proof on the claimant; time and cost
Negotiation backed by a prepared complaintPreserving the commercial relationshipDepends on credibility of the escalation threat
Practical point

Before escalating an access dispute, build a written record: a formal application that meets the operator's published registration conditions, the operator's response, and evidence of spare capacity from public or user-only disclosures. Under the pipeline measures an operator that rejects an application must give written reasons, and a clean paper trail is what turns a commercial grievance into an enforceable complaint.

A worked example

Consider a foreign-invested gas trader that wants to bring LNG cargoes into a coastal terminal and move gas inland. The illustrative sequence would be: register as a user under the terminal and pipeline operators' published conditions; apply for terminal window and pipeline capacity; if the reply is a refusal, request written reasons and the capacity information users are entitled to receive; compare the reasons with the published allocation rules; then decide, with PRC counsel, whether to seek coordination by the energy authority, complain to the market regulator or negotiate.

Throughout, the trader should keep its own licences and any negative list conditions for its activity in order, because a defective user position weakens any complaint.

Access to infrastructure in China: points for operators and investors

For owners of networks, access obligations are a compliance and valuation issue. Investors in pipelines, storage, terminals, data centres or logistics hubs should test during due diligence whether the asset is subject to an access code, how tariffs are set, and whether any affiliated trading business benefits from the asset in ways that could be challenged as discriminatory. Operators should publish compliant access rules, apply them consistently, keep capacity calculations auditable and document the reasons for any refusal.

Operator compliance checklist

  • Published registration conditions, application procedures and capacity allocation rules that match actual practice.
  • Financial separation between network services and any affiliated trading or sales business.
  • A response log showing dates, decisions and written reasons for each application.
  • Auditable capacity calculations and a process for releasing unused capacity.
  • Standard contracts reviewed for unfair or discriminatory terms.
  • Systems ready for the more detailed disclosure and reporting that applies from 2027.

Transaction documents should reflect the same analysis. Share purchase agreements for regulated assets benefit from warranties on access-code compliance, complaints and penalties, and joint venture agreements should state how capacity will be offered to shareholders and third parties so that preferential treatment of a shareholder-trader does not become a discrimination complaint after closing.

Where a project also involves public bodies, the fair competition review regime may constrain exclusive rights or preferential terms that local governments can grant. Related sector issues are covered on our oil, gas and petrochemicals and power and electricity pages.

International comparison: EU, US, Hong Kong and ASEAN

Foreign participants often come with expectations shaped at home, and it helps to see where access to infrastructure in China resembles other systems. In the EU, regulated third-party access to gas and electricity networks is built into the energy market legislation, with unbundling of network and supply activities, and competition law recognises a narrow essential facilities doctrine. The Digital Markets Act adds specific access and interoperability duties for designated gatekeepers.

In the US, refusal-to-deal claims under the Sherman Act face a demanding standard after the Supreme Court's 2004 Trinko decision, so access is mainly secured through sector regulation such as federal open-access rules for interstate pipelines and transmission. Hong Kong's Competition Ordinance prohibits abuse of a substantial degree of market power, and several ASEAN states run regulated access regimes for telecoms and energy.

China's approach sits between these models: detailed sector codes for oil and gas, broader principles for power and telecoms, and an Anti-Monopoly Law that names essential facilities expressly. For cross-border investors, the lesson is to treat access to infrastructure in China as a combination of a regulatory licence condition and a competition risk, and to model both when valuing an asset or planning market entry.

How TRW & Co helps

Our Shenzhen representative office advises international and Chinese clients on the cross-border and commercial side of infrastructure access. We help users and investors map the applicable access and competition rules as part of the Chinese legal environment, structure capacity and service arrangements, negotiate access, offtake and joint venture documents, and benchmark Chinese regimes against those in other jurisdictions where the client operates.

We prepare strategy for complaints and negotiations, manage evidence and timelines, and advise on the laws of jurisdictions where our lawyers are qualified. Where PRC legal opinions, regulatory complaints, filings or court proceedings are needed, we work alongside licensed PRC law firms and coordinate the overall workstream. Contact us to discuss an access issue.

Frequently asked questions

Does Chinese law recognise an essential facilities doctrine?

Yes, in substance. SAMR's 2023 provisions on abuse of dominance list refusing reasonable use of an essential facility as a form of refusal to deal, and set out factors such as the feasibility of building an alternative and the counterparty's dependence on the facility. The doctrine only applies where the facility owner holds a dominant position and has no legitimate reason for refusing.

Do the 2025 pipeline access measures cover city gas networks?

No. NDRC Order No. 33 applies to oil and gas pipeline facilities in mainland China and its jurisdictional waters, including LNG terminals and storage, but excludes urban gas facilities. Conduct by city gas distributors, such as tying connection works to supply, is more commonly addressed under local utility rules and the Anti-Monopoly Law.

Can a foreign-invested company rely on these access rights?

The pipeline measures protect qualified users that meet the operator's published registration conditions, and the Anti-Monopoly Law applies regardless of the nationality of the parties. A foreign-invested enterprise must still hold any licence needed for its own activity, such as gas trading, and comply with the foreign investment negative list for the relevant sector.

Which is better: a regulator complaint or a court claim?

It depends on the goal. A sector regulator can order service quickly where a clear access rule has been breached. A SAMR complaint suits broader competition concerns but proceeds at the authority's discretion. A civil claim can produce damages but requires the claimant to prove dominance and abuse. Many disputes are resolved by negotiation once a credible complaint is prepared.

What should investors check in infrastructure due diligence?

Investors should identify whether the asset is subject to an access code, how its tariffs are set or approved, whether affiliated businesses receive preferential treatment, what capacity disclosures the operator must make, and whether there have been complaints or penalties. These factors affect revenue assumptions and the risk of regulatory intervention after closing.

Sources

  1. NDRC Order No. 33: Measures for the Supervision of Fair and Open Access to Oil and Gas Pipeline Network Facilities (State Council Gazette)
  2. NDRC interpretation of the oil and gas pipeline fair access measures
  3. SAMR Order No. 66: Provisions on the Prohibition of Abuse of Dominant Market Positions (State Council Gazette)
  4. Xinhua: NEA measures on information disclosure and reporting for pipeline fair access